Tuesday 7 October 08 - 10:28
 

Marine Civils by David Foxwell

Deep Water Jetty for New Orkney Ferry Service

A new deep water jetty for the ro-ro ferries - the Hjaltland and Hrossey - has achieved 'minimum berthing status' at Kirkwall in the Orkney Islands, and is on course for completion next year, at which time it will also begin to be used by the large number of cruise ships that visit the Orkney islands nowadays, as well as cargo vessels calling at Kirkwall.

The new jetty at Kirkwall will provide a berthing facility for ferries, cruise ships and general cargo vessels.
The new jetty at Kirkwall will provide a berthing facility for ferries, cruise ships and general cargo vessels.

The new facility, the Hatston Terminal, is designed to service the two new Northlink ferries, which make regular sailings from the islands to Aberdeen and the Shetland Isles, and has three main components - new landside facilities (with a 1,500m 2terminal), the new jetty with rock causeway to it, and a new linkspan, linking the jetty and the ship's using it, which is being provided by McGregor.

The new facility takes the form of a 'dogleg' pier with four berthing faces. It is being constructed using a concrete deck on tubular piles which have been driven into the bedrock and encased with reinforced concrete.

The project is being carried out by R J McLeod (Contractors) Ltd and the company's subcontractors Harbour and General Works who are primarily responsible for the civils work on the project. Consultants Arch Henderson & Partners are acting as project engineers on behalf of the Department of Engineering and Technical Services in the Orkney Islands Council.

Prior to construction work starting, HR Wallingford was commissioned to carry out a wave study for the new facility to determine whether there were any conditions which might adversely affect berthing operations, and Fugro was contracted to carry out the necessary site investigation.

As Stewart Craigie in the Orkney Islands Council's Engineering & Technical Services Department explained, the design produced by R J McLeod uses a series of horizontally braced frames at deck level, which are bolted to the tubular piles. The frames support pre-cast concrete units, with a 750mm thick concrete deck.

Craigie said a total of 466 tubular steel piles range from 610mm diameter sections to 1,067mm diameter were required, the longest being 24m in length. To protect them from corrosion, the piles have an Impressed Current Cathodic Protection (ICCP) system.

As Craigie explained, the entire project is a huge undertaking, requiring approximately 15,000m 3of concrete and 1,300t of reinforcement, so R J McLeod had to set up a 'batching plant' to prepare and supply the concrete required.

The quartet of berthing faces will be 153m, 116m, 161m and 225m long respectively, and are dimensioned to accommodate, respectively, cargo ships, the Northlink ferries and cruise ships.

The ro-ro berth should be complete in July 2003, said Craigie.

Images for this article - click to enlarge

The new jetty at Kirkwall will provide a berthing facility for ferries, cruise ships and general cargo vessels.
The jetty consists of steel piles with horizontal frames and a concrete top.

Unless otherwise stated, all images copyright © Mercator Media 2008. This does not exclude the owner's assertion of copyright over the material.

Related products

For more information on products mentioned within this article visit

HR Wallingford Ltd

MTU IRONMEN