Largest Limpet Dam In Action at the Port of Felixstowe

John Martin Construction Ltd has recently undertaken some essential maintenance work at the Port of Felixstowe.

The limpet dam for Felistowe enabled quayside works to a depth of 12m.
The limpet dam for Felistowe enabled quayside works to a depth of 12m.

The scope of the work included the installation of low level ground anchors and strengthening work to the sheet piled quay wall.

The work was carried out using the largest limpet dam that has been manufactured by John Martin, at its plant fabrication depot near Norwich UK.

The limpet was 12m deep, 5m wide and weighed 32 tonnes.

The use of a limpet dam allowed work to be carried out in safety while minimising any disruption to traffic at the port.

MJ Information No: 17936

Images for this article - click to enlarge

The limpet dam for Felistowe enabled quayside works to a depth of 12m.

All images copyright © Mercator Media 2008

Related products

For more information on products mentioned within this article visit

Nuttall John Martin Ltd

TaylotFuel_Skyscraper_0508