Dover Ramp Contract Completed

Edmund Nuttall Ltd successfully installed prefabricated vehicle and passenger walkway ramps last month under their design and construct contract with Dover Harbour Board UK for the new Pier F and Berths 8 & 9.

Bonn & Mees floating sheerlegs Matador 3 lifts a high level passenger walkway into position.
Bonn & Mees floating sheerlegs Matador 3 lifts a high level passenger walkway into position.

Two 60m long vehicle decks, weighing in excess of 300 tons, were positioned by the 1,500 ton capacity floating sheerlegs Matador 3 , operated by Rotterdam's Bonn & Mees.

The fully fitted assemblies were built in and shipped from Holland to be positioned over a three day period by subcontractor Hollandia BV.

Together with a high level passenger walkway, the ramps are hydraulically operated to speed ro-ro operations.

Separate stair tower buildings have been provided for the new Berths 8 & 9, with the 220m long fully fendered pier able to accept vessels up to 27,000 tons.

MJ Information No: 20118

Images for this article - click to enlarge

Bonn & Mees floating sheerlegs Matador 3 lifts a high level passenger walkway into position.
(Below): A spectacular view showing the new Berths 8 & 9 at Dover taking shape.

All images copyright © Mercator Media 2008

Related products

For more information on products mentioned within this article visit

Edmund Nuttall Ltd

TaylotFuel_Skyscraper_0508