Tuesday 2 December 08 - 01:31
 

Works In Progress

Teamwork Rocks Against the Sea

Team Van Oord is nearing completion of Phase One of the High Knock to Dymchurch Redoubt Sea Defences near Dover in the UK. The works for the UK Environment Agency are to upgrade existing defences and maintain the protection they provide to some 2,500 homes lying below sea level in Dymchurch and the wider areas of Romney Marsh.

The new seawall is being built at a rate of 20m per day.
The new seawall is being built at a rate of 20m per day.

The £9M scheme is being carried out under the National Contractors Framework Agreement for which Team Van Oord holds a five year agency to carry out planned and emergency coastal works for the Environment Agency. Team Van Oord partners include Van Oord UK Ltd, J T Mackley Ltd, and T J Brent Ltd. The advantage of NCF for the client is fixed prices and time saved by the contractor already being on board, with a tendering and documentation process not being required for every separate project. The Team Van Oord agency has a targeted workload threshold valued at some £60m over the five year period in an arrangement that leaves the Environment Agency free to tender some projects on a non-NCF basis.

Through a process of Early Contractor Involvement, Van Oord UK Ltd, in collaboration with the Environment Agency and project designers Jacobs Babtie, instigated a redesign of the revetment structure in 2003, with design testing of scale model defences at Technical University Delft in the Netherlands leading to a finalised plan by September 2004. Workability sessions and other planning took place over the winter. When the EA budget came through in April of this year, all that was required was to mobilise equipment for a start of works in May. Team Van Oord was three weeks ahead of schedule when visited by Maritime Journal last month, with Phase One works expected to finish by late November.

Phase One involves the construction of 1,200m of concrete seawall spaced some 2m seawards from the promenade atop the existing defences. The gap is backfilled with debris from the excavation of footings and topped with concrete to give a new promenade some 7m wide. The existing concrete slope up to the old defenses has deteriorated under the relentless pounding of wind driven seas off the Strait of Dover and did little to slow or disperse the energy of the onrushing waves. There was risk of breaching, and overtopping was a recurring problem for traffic on the busy A259 immediately behind and below the old defences.

To eliminate these threats, 150,000 tons of rock armour is being placed over a length of 1,500m to protect the toe and slope of the existing structures.

Phase Two will start in the spring of 2006, involving the construction of a further 900m on concrete wall to the immediate south of Phase One as well as an additional 200,000 tons of rock revetment. Team Van Oord is also constructing seven new sets of steps and three new access ramps for maintenance and emergency vehicles along the entire project.

The new rock revetment over the existing concrete slope will be placed to an average depth of 2.4m and consists of irregular granite blocks produced by Stema Shipping at their dedicated rock armour quarry at Larvik in Norway.

The granite is loaded onto a 20,000 ton capacity flat barge and towed to an agreed anchorage point off the site. Approximately 2,000 tons at a time is loaded onto a smaller Stema transhipment barge and brought as close to shore as possible just before the high tide, when an onboard loading shovel tips the rocks, each one weighing between three to ten tons, onto the beach.

During a five hour low tide window twice a day, Team Van Oord workers take to the beach and defences. An excavation team prepares 20m of footings per day, which is the same rate at which the concreting team is able to place forms and pour the seawall. Meanwhile, excavators equipped with grab attachments pull rock armour from the tide and place them two at a time in the sand filled bed of a large dump truck which delivers them to a powerful 100 ton capacity final placement excavator, which will eventually bring rock back as far as the toe of the new seawall.

Unlike the old concrete slope it sits atop, this irregular, multifaced rock armour effectively dissipates the force of the waves before they even reach the new seawall and will significantly reduce overtopping.

For reasons of plant removal access, Phase Two must finish next year before the final rock armour is placed for Phase One, at which time the people and places behind these renewed defences can expect another 50 years of the vital protection they need.

MJInformation No: 21123

Images for this article - click to enlarge

The new seawall is being built at a rate of 20m per day.
Van Oords 100 ton mobile crane places the rock armour one piece at a time. Rock armour is retrieved from the beach at low tide.

Unless otherwise stated, all images copyright © Mercator Media 2008. This does not exclude the owner's assertion of copyright over the material.

Related products

For more information on products mentioned within this article visit

Van Oord UK Ltd

MTU IRONMEN