Suction bucket jackets for Borkum Riffgrund 2

Industry Database

The final load of foundations for Borkum Riffgrund 2 have left Szczecin, concluding a ST3 Offshore project for Danish energy concern Ørsted.

ST3 Offshore reports that the load process was very complicated, with the preparation of the documentation alone taking several months. Methods had to be accepted by the insurer, classification societies and of course by the client. Setting the constructions in grilleages required extreme precision and depended on weather conditions, with the first load out taking four days.

The 7th load with the last two jackets left Szczecin on the 12 of June. “We are satisfied with the project’s execution” – said Adam Kowalski, vice president of the management board of ST3 Offshore. At time of writing 18 out of the 20 jackets had been delivered to the client and four of them set on the wind farm.

The jackets produced for this project consist of foundations designed on an equilateral triangle plan (footprint: 28m), 60 m high, set on suction buckets.

The Borkum Riffgrund 2 Offshore Windfarm has a target power generation capacity of 450MW using turbines mounted on a total of 56 steel foundations where 20 foundations are jackets and the remaining 36 foundations are monopiles. It will feature the largest wind turbines in German waters: 56 MHI Vestas 8 MW wind turbines with rotor spans of 164 metres.

The company is negotiating new contracts, but will not disclose details.

By Jake Frith

Latest Press Releases

Iskes Towage names twin Damen ASD Tugs 3212 Mars and Mercurius

Two of Iskes Towage’s vessels, the Damen ASD Tugs 3212 Mars and Mercurius, have been officially name... Read more

A Huge Success for Datum Electronics’ Cutting-Edge Marine Shaft Power Meter at SMM Hamburg

SMM Hamburg, the biggest maritime fair of 2018, ended recently and Datum Electronics, together with ... Read more

Damen supplies DOP150 submersible dredge pump for new power plant project in Brazil

Damen has supplied a DOP150 submersible dredge pump to Brazilian civil engineering contractor BELOV.... Read more

Damen performs tank testing of new FCS 7011

Damen Shipyards Group has carried out tank testing of its 70-metre Fast Crew Supplier (FCS) 7011. Th... Read more

Damen Shipyards Galati opens historical exhibition as part of continuing 125 year anniversary celebrations

Displaying an extensive collection of historical maritime memorabilia, Damen Shipyards Galati has op... Read more

Damen Chairman meets Romanian Minister of Economy

3 September 2018: Chairman and owner of Damen Shipyards Group Kommer Damen has held a meeting with t... Read more

View all