Wind farm contract for German North Sea

Germany’s Hochtief Construction has been awarded the contract for another offshore wind farm.

Global Tech 1 will be the first offshore wind farm where Beluga Hochtief Offshore’s special jack-up vessel will be used.
Global Tech 1 will be the first offshore wind farm where Beluga Hochtief Offshore’s special jack-up vessel will be used.

From mid-2012, the Hochtief subsidiary is expected to start constructing the Global Tech I wind farm in the German North Sea in a contract valued at €175m. The client is the project company Global Tech Offshore Wind in which several energy suppliers, energy trading companies and a number of other companies have a share.

Global Tech Offshore Wind GmbH is the project company that will build and operate the offshore wind farm. The company’s shareholders are the two energy suppliers Stadtwerke München GmbH and HSE AG (Darmstadt), the European energy trading company EGL AG, Esportes Offshore Beteiligungs GmbH and the two project development companies Norderland Projekt GmbH and Windreich AG.

Global Tech is one of the first offshore wind farms that built in the German North Sea.

At the site some 110 km northwest of Cuxhaven, Hochtief will first anchor 80 foundations, each with a weight of 950 tons, in the seabed at a depth of 40m. The 5MW wind turbines, reaching 150m above the water, will then be mounted using group owned special platforms.

The wind farm is being built in the German Exclusive Economic Zone (EEZ), outside marine protection areas. Germany’s Federal Maritime and Hydrographic Agency (BSH) granted its approval for the 80 wind power stations and the associated transformer station as early as 2006. According to the current planning status, Global Tech will be connected to the power grid in 2012 and, after having reached full capacity in 2013, will deliver electricity for an equivalent of 445,000 households with an average consumption of 3,130 kilowatt hours.

In this project, Beluga Hochtief Offshore’s special jack-up vessel will be used for the first time. Hochtief also has developed a logistics concept which promises to reduce the construction time significantly.

The Group expects annual sales of almost half a million euros from its entire offshore business. The client will invest approximately €1.3bn into the offshore wind farm, with a total capacity of 400 megawatts.