The funding boost will support a total of ten projects under the Structural Materials and Manufacturing Process (SMMP) scheme.
REINFORCED POLYMER MATERIALS
One initiative set to receive backing is the RePOWER (Reinforced Polymers for Wave Energy) project, which has received £249,614 to focus on the assessment of hybrid polymers as the key structural material for so called ‘point absorber’ WECs in an advanced stage of development.
As Mairead Atcheson Founder and Senior Engineer at project coordinator Cruz Atcheson Consulting Engineers, explains, the fact that the project is applied to WECs that have already reached, or that are reaching, a high TRL (Technology Readiness Level) means it has the potential to ‘accelerate cost reduction in technologies capable of having a significant near to medium term impact in Scotland.’
The finance will enable Cruz Atcheson to work alongside partners at Carnegie Wave Energy, CorPower Ocean, Arup Consulting Engineers, DNV-GL and the National Composites Centre over a twelve month period to assess the viability of candidate materials, manufacturing processes and concept designs in an effort to better understand which (if any) carry the potential for significant cost reduction while simultaneously meeting strict targets relating to performance, reliability and ‘survivability.’ If given the go ahead, subsequent stages are likely to cover a range of experimental and field trials for the most promising material and design combinations.
“Because RePOWER involves a large consortium of technology developers, independent engineering consultancies, material specialists and a certification body, it is also expected that the key outputs will be directly applicable to a range of WECs and other offshore technologies,” says Atcheson.
PRIME MOVERS
In Atcheson’s view, the developers of any WEC ‘prime mover’ face a range of conflicting challenges – particularly in minimising full life cycle costs while meeting reliability and survivability targets. In rising to these challenges, she says that hybrid structures with reinforced polymers may help by increasing the prime mover life span without compromising its structural integrity.
“There are a plethora of examples in the aerospace and maritime industries that involve the use of similar materials in harsh environments – and RePOWER tries to build on those experiences while applying realistic constraints that are specific to wave energy applications,” she says.
If this initial stage finishes successfully, Atcheson explains that Wave Energy Scotland may decide to grant funding for additional stages focused on commercial development and an assessment of alternative application of the candidate materials.
“These mostly likely stem beyond wave energy, but RePOWER’s sole focus is in contributing to Wave Energy Scotland’s goal of accelerating the development of cost effective wave energy generation systems,” she adds.
COMPOSITES
Elsewhere, another project – dubbed HydroComp – will also focus on an assessment of the viability of hybrid Fibre Reinforced Polymer (FRP) prime movers for point absorber WECs. This project – led by CorPower Ocean, with support from Balmoral Offshore Engineering and Wave Venture – will entail a wide range of activities, including the benchmarking of target ‘outcome metrics’ relating to affordability, availability, survivability and performance, as well the overall impact on the Levelised Cost of Energy.
“Initial evaluation and trialling, coupled with our experience with composite materials, suggests the benefits of using a lightweight, durable solution in all aspects of product manufacture and in-service performance,” says Brian Bakewell, Industrial Designer at Balmoral Offshore Engineering, which will contribute expertise in structural design, materials and production for offshore environments.
Because existing reinforced composites have proven to be ‘unsuitable’ for long-term solutions in harsh marine environments Bakewell also reveals that expected service life expectancies for WEC products require a solution capable of surviving the ‘extreme rigours of a dynamic marine environment with minimum maintenance and servicing.’
“It must also provide reliable and protective encasement of the operational equipment deriving the energy conversion,” he adds.
POLYSHELL
Another interesting initiative funded under the SMMP scheme is Polyshell – a £244,500 project aiming to assess the potential of employing high performance thermoplastic elastomers as the outer shell of wave energy devices.
The project is headed up by technology from ideas (TFI), an Irish seed investment and commercialisation company that has developed polymer components to manage and significantly reduce loads within mooring systems. As Noel Halloran CEO at TFI, explains, the Polyshell project provides an opportunity to ascertain if the concepts the company uses in mooring systems can be successfully applied to larger hull structures.
“The Polyshell project is taking our materials expertise and creating a flexible polymer hull structure for a WEC. Permitting the hull to bend in defined ways reduces the loads on it, thus enhancing survivability and reducing cost,” he says.
In aiming towards this objective, the team will validate the suitability of the polymer material used in the TFI mooring components. Amongst other things, it will also developing and model the complex 3D shaping of the surfaces, carry out engineering design and investigate the overall impact on LCOE (Levelised Cost of Energy).
Halloran says that the project will also entail a ‘significant amount’ of market engagement – and he reveals that the company has already received a good reaction from some current WEC developers, leading to preliminary discussions about how it applies to their devices.
“This will enable us to identify issues and opportunities which can be addressed in a stage two WES project and also to identify commercial opportunities,” he says. “The material and flexible structure approach are applicable to all marine structures, not just for WEC devices. We believe there is a huge potential maritime market for Polyshell, in both the renewable and non-renewable areas,” he added.
By Andrew Williams