Aberdeen Harbour announces contractor for Torry Quay development – by David Foxwell
Aberdeen Harbour Board has awarded a £14m contract to construction company McLaughlin & Harvey for the first phase of the Torry Quay redevelopment. The Northern Ireland firm will undertake works on the initial stage of a three phase project worth £30m, which is due to get underway this month.
The first, which will take 18 months to complete, will include the demolition of the existing wharves at Torry Quay and replacing them with 300m of realigned, deep draught quays constructed from steel piles and reinforced concrete. These new quays are designed to be more suitable for modern, deep draught ships and heavy cargoes.
On completion the project, which is part of Aberdeen Harbour Board’s £65m development strategy, will result in over 500m of new deep water berths and more than seven hectares of back up land on the south side of the River Dee.
Ken Reilly, engineering director of Aberdeen Harbour said, ‘We are delighted that work is about to start on this redevelopment. Aberdeen Harbour is an integral part of the north-east’s economy and it is essential that we offer port users new and improved facilities as vessels increase in size. Substantial consultation has taken place with all the stakeholders in the area to ensure the works are carried out without disturbance to the environment, particularly protected species of salmon and dolphin that frequently visit the harbour.’
Aberdeen Harbour handles around five million tons of cargo, valued at £1.5bn, and growing levels of shipping for a wide range of industries. With more than £200m invested by the Board in the last 30 years, the port is one of the most modern in Europe.