Work starts at former power station site

The dock modification works are due to commence during the summer and will involve the widening of the existing dock, excavation of materials and dredging The dock modification works are due to commence during the summer and will involve the widening of the existing dock, excavation of materials and dredging
Industry Database

Advance Northumberland has reached a significant milestone in the redevelopment of the former Blyth Power Station Enterprise Zone in Blyth, UK.

The contract to undertake the ground works and dock extension has been awarded to Farrans Building and Civil Engineering, following a competitive tender process.

Since acquiring the site Advance Northumberland have made significant progress over the last 18 months including securing funding, obtaining planning permission and finding a main contractor to undertake the programme of work. The main purpose of this activity is to attract investment to bring the site back into use, creating new jobs and boosting the local and regional economy. The infrastructure investment and clean-up works will assist greatly in the attraction of private sector investors to this difficult brownfield site that has been standing derelict since 2003. Despite these challenges, the site is also recognised regionally as having many strategic strengths, enhanced by its designation as an Enterprise Zone.

The dock modification works are due to commence during the summer and will involve the widening of the existing dock, excavation of materials and dredging. The works are expected to take 18 months to complete.

Farrans Regional Director for Civil Engineering in England, Neil Barnes, commented:  “We are delighted to have been awarded the contract for the first phase of Northumberland Energy Park.

“This is an exciting project which will bolster the economic prosperity of the Northumberland region – both during the construction phase and in the years ahead.

“Having enjoyed a presence in the North East for some years, as well as carrying out a wealth of marine and remediation sector projects across the UK, we look forward to drawing upon this knowledge and experience on-site in the months ahead”.

The project received £4,440,736 from the Government’s Local Growth Deal through the North East Local Enterprise Partnership (LEP). The Local Growth Deal is supporting major capital investments to promote innovation, economic and skills infrastructure and sustainable transport as part of the North East Growth Deal.

By Jake Frith

Latest Press Releases

Concordia Damen ships 18 hulls from Shanghai to Rotterdam

On Monday, 17th June, heavy-lift vessel Black Marlin departed Shanghai. On deck with eighteen Concor... Read more

Damen Shipyards welcomes Mexican cadets and crew of the ARM Cuauhtémoc during Sail Scheveningen

Due to the port visit of the Mexican Sail Training Vessel ARM Cuauhtémoc to Scheveningen, the Nether... Read more

Keel laid for the first of Damen’s revolutionary new FCS 7011 Crew Change

Two and a half years on from the genesis of the FCS 7011 concept in response to extensive feedback f... Read more

First European conversion of a dredger to dual-fuel LNG / MGO departs Damen Shiprepair Dunkerque

First European conversion of a dredger to dual-fuel LNG / MGO departs Damen Shiprepair Dunkerque Read more

Damen Oskarshamnsvarvet Sweden achieves coveted AAA credit rating

Damen Oskarshamnsvarvet Sweden achieves coveted AAA credit rating Read more

Damen signs Phase II contract with International Organization for Migration

Damen signs Phase II contract with International Organization for Migration for nine additional SAR... Read more

View all