Dredging Delivers Denmarks New Container Terminal

Dredging contractor Rohde Nielsen A/S has moved more than 7m m3 of sand in helping to construct new container terminals at Aarhus Harbour in Denmark. The projects origins date to 1998 when a 25 year plan for the development of what is Denmarks largest and busiest port was published. Work in the harbour area was to concentrate on the container port. Phase 1 of the project was completed by 2001, with Rohde Nielsen A/S playing a significant role in shifting 5.5m m3 of sand.

00_39557_AArhus

When Phase 2 started last year

,

Rohde Nielsen’s dredgers

Kronborg R

,

Freja R

and

Sif R started work on the new Container Terminal East

,

which would lift the Baltic Sea hub into the ranks of the world’s top 100 container ports. S

and

was pumped from another part of Aarhus Bay

,

where Danish authorities had given permission for winning.

Despite the proximity to the new area thesse areas were not the easiest or most accessible

,

with the s

and

won from some 20m below sea level.

Each round trip from the winning area to the unloading area

and

back took each dredger five hours. Working on a 24/7 basis

,

each vessel made almost five complete voyages per day

,

moving a total of some 6.4m m3 of s

and

. Rohde Nielsen kept within what were perhaps the strictest environmental regulations anywhere in the world.

More than 3.5m m3 was required to create l

and

on which two new container terminals were to be built. Between these two terminals a new artificial basin gradually appeared

,

which was economically filled to a depth of 4

,

5m by the split hopper dredger Sif R

,

operating whilst there was still access to the basin from the rest of the harbour.

Danish contractors MT Højgaard started work on a new pier

,

with Rohde Nielen as subcontractor. After MJ Højgaard had placed the sheet piling

,

dredgers began rainbowing s

and

behind the artificial barrier to create the basis for a new quayside area which was later covered with concrete. Some 900

,

000 m3 of s

and

was delivered or this component of the project.

Rohde Nielsen also undertook environmental works on the south east side of the container terminal

,

filling an area that had been used as a dumping ground or harbour waste material for many years.