A heavy lift contractor has broken a record with the lift of a 17,000 metric tonne heavy process module which it says is the heaviest crane lift ever undertaken at sea.

Heerema has nstalled TotalEnergies’ biggest Tyra II topside on the last remaining bare jacket at the Tyra field

Record lift

Source: Heerema Marine Contractors

Heerema has nstalled TotalEnergies’ biggest Tyra II topside on the last remaining bare jacket at the Tyra field

Heerema Marine Contractors has safely installed TotalEnergies’ biggest Tyra II topside on the last remaining bare jacket at the Tyra field.

”The safe and successful installation of the 17,000 tonne TEG module is a fantastic milestone for Heerema and Sleipnir. The record-breaking lift demonstrated the vessel’s capacity to install enormous structures at sea,” said Michel Hendriks, COO for Heerema.

”We are proud to have contributed to this key milestone in TotalEnergies’ and Danish Underground Consortium Partners’ Tyra Redevelopment project. The project’s success resulted from six years of close partnership and collaboration between all parties involved.”

Careful preparation

Nothing was left to chance during the lift, when the two crane drivers, with the support of more than 260 offshore workers onboard the vessel Sleipnir, lifted what corresponds to the weight of around two Eiffel Towers.

The lift has been prepared for years and every single step prior to, during and post lifting has been outlined in a several hundred pages-long manual prepared by Heerema Marine Contractors and TotalEnergies.

After the processing module arrived at the Tyra field on 3 October, the offshore crew immediately started to remove the sea fastening below the 47-metre module. The sea fastening helped to ensure a safe and stable journey from Indonesia.

Thanks to great weather conditions, the crane drivers got the green light to lift the module into its final position less than 24 hours after its arrival and four days ahead of schedule.

It required a lot of coordination, horsepower, and precision when the crew on Sleipnir had to install the enormous process module. With two enormous crane hooks, the team picked up the process module from the heavy transport vessel GPO Emerald. They then sailed one nautical mile to the final bare jacket while they raised the module by nine metres to then lower it onto the six legs.

In the coming weeks, the final Tyra II pieces – two bridges and a flare – will be installed. When all connections are welded, the installation team will hand over the baton to the TotalEnergies hook-up and commissioning team, who will focus on completing and powering up the installed platforms and reconnecting them to the existing North Sea infrastructure.