Seamark Placed for Margate Treatment Project
The offshore components of Southern Waters £
Main contractors are a consortium of
Black
and
Veatch
and
Costain,
with
Cornwall based
Seacore Ltd responsible for the marine side of the project. A new 1.8m diameter storm water discharge pipeline has been tunnelled beneath the seabed, emerging 600m offshore into a pre-dug 13m by 8m by 7m deep pit then upwards to a diffuser
with
two Tideflex Duckbill valves centred approximately 1.8m above the seabed. The pit was then filled
with
a grouted granular fill topped
with
two concrete mattresses wired together
and
a 200mm concrete topping.
Marking the diffuser was essential, being in a busy area for both commercial
and
leisure craft.
Anglian Marine Services
and
Haven Ports Ltd utilising their jack-up barge Haven Seaway, assisted by Felixarc Marine’s multi-cat Gray Mammoth, installed a fixed structure in the form of a steel triangular dolphin
with
sides approximately 5m in length. The whole structure is around 18m high
and
comprises three sections connected by conical spurs
and
sockets in each section. The two lower sections are embedded
with
in the pit
with
three short lengths emerging from the pit fill to which the main upper section is attached.
The northernmost leg has a double fabricated fender
with
bump stops protecting a vertical ladder providing access to the maintenance platform
and
safety cage at the very top of the structure, 6.2m above Ordnance Datum Newlyn
and
3.9m above MHWS. Lowestoft based Pelangi International provided the required navigational marks comprising top mark, radar reflector
and
a solar powered light
and
battery.
By Peter Barker